Construction will cause a week’s worth of overnight closures on both sides of the 605 Freeway starting Monday, potentially causing what could be a traffic nightmare for early-morning commuters.
The closures, which began at Monday evening, will last through the morning each day until Saturday, Dec. 7.
According to the California Department of Transportation, the scheduled construction includes concrete work, asphalt paving, k-rail placement, striping, guardrail work, sign removal and drainage work.
The closures are subject to change if weather does not permit work to be completed. The full schedule is as follows:
“All corresponding on- and off-ramps will be closed sequentially as work progresses. No two consecutive ramps will be closed at the same time,” said a statement from Caltrans officials.
They urge people to use detours, which include either I-710 or I-5. Officials have installed signs to guide drivers.
There will also be a number of lane and ramp closures through the slated closures, lasting through Saturday evening. Those closures include (between 8 p.m. and 6 a.m.):
The construction is a part of the “Super 605” corridor project, which aims to rehabilitate the freeway from Long Beach to the San Gabriel Valley, officials said.
“A total of $250 million in construction costs is funded with $238 million from the federal Infrastructure Investment and Jobs Act, and more than $20.6 million from Senate Bill 1, the Road Repair and Accountability Act of 2017,” said a statement from Caltrans.
It’s the second major freeway closure going into effect on Monday, with a major portion of SR-91 scheduled to undergo weeks worth of overnight closures for a different project in Riverside County.